Our project will be moved to the new development environment form the current NWDI environment. Before the movement, we need to activate and release all the activities present in the current NWDI environment. What steps need to be followed for the same?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 02, 2008 at 09:07 AM

    Hi,

    You can activate and release your activities from NWDS. Activate them from open activity view,

    And from transport view you can release them.

    And when you release them just select all the activities waiting to transport, and release them.

    dont release one by one activity.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Michael Voss

      Hi,

      thank you for your references.

      I've got some good news about my problem, I could solve it.

      I've rebooted the nwdi server (where the requests are running and running and running...), and now I can see the "waiting" node and can go on with the transport workflow. Let me say it like this, the reboot solved the problem.

      Thank you for your quick and good help,

      Stefan

  • avatar image
    Former Member
    Sep 05, 2008 at 03:32 AM

    Released activities are not available in consolidation compartment.