Hi

I have a material with SLED. So when the expiry date comes say 03/09/08 for example, system should transfer automatically to quality stock on that day or some day before the expiry date so that to stop from GI, PGI or other kind of transfer. How to do that?

Thanks & Regds

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 02, 2008 at 06:59 AM

    Hi m,

    you can do it by QA07.

    Tick on 'Block Batch' when expire date is reached.

    You can then create background job to run this on regular interval.

    Use QA05 for it.

    reagards,

    Chintan