I have a material with SLED. So when the expiry date comes say 03/09/08 for example, system should transfer automatically to quality stock on that day or some day before the expiry date so that to stop from GI, PGI or other kind of transfer. How to do that?
Thanks & Regds
Hi m,
you can do it by QA07.
Tick on 'Block Batch' when expire date is reached.
You can then create background job to run this on regular interval.
Use QA05 for it.
reagards,
Chintan