Sales pricing

Dear All,

I am creating Inquiry with VA11 and assign it to one WBSE which is Billing Element and Assign DIP profile to it.

I want to create Quatation and Billing Plane for that with the refrence of that inquiry .

When i use DP81 it shows the error message (Expendature items not found).I am sending the full error message as given below

No expenditure items found

Message no. VPK1310

Diagnosis

No expenditure items matching the selection were found.

System Response

No processing possible.

Procedure

Resource-related billing contains no expenditures for the posting timeframe you specified. Specify a different timeframe.

In the case of quotations, there are no costs in the project or service order. Check whether any have been planned.

Not able to understand the Time Frame .

And for Qutotation there is price in Inquiry.

Please help me in doing same.

regards.

Sukhveer.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 02, 2008 at 08:22 AM

    You need to have cost planned for the WBS Element. This cost plan can be automatic or manual. Only then you can have sales pricing.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      We have exactly the same problem and we have come to our end. Any help on this subject. I can say that the time frame for the plan and the processing of DP81 is the same date. today's date. We are testing. Our DIP check is green no overlaps or errors there.

  • avatar image
    Former Member
    Oct 15, 2008 at 04:49 AM

    Dear,

    Its problem of SD side time frame is not defined there.

    Its answred.