Skip to Content

How to restore Light_Optimize process chain in production in BPC NW 10.1 (classic)

Hello,

For some very strange reason, /CPMB/Light_Optimize process chain disappeared in the production system. It cause scheduled light_optimization data manager package to fail.

1. On BW side. /CPMB/Light_Optimize process chain is not on the list in RSPC. When looking at SE16 --> RSPCCHAIN, there is only D version of /CPMB/LIGHT_OPTIMIZE chain exists. Unlike other standard BPC chains, they all have A and M version together with D version.

2. Have attempted to transport this chain up to Production. But did not make any difference.

3. As it is a production system, not sure what other options that we could have to get this chain back, build one from scratch?

Wondering if anyone has experienced something similar before? Or any thoughts on this?

Many thanks

Jingjing


Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Oct 31, 2016 at 12:18 PM

    What about SE38 UJS_ACTIVATE_CONTENT?

    Activate BI Business Content option.

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 31, 2016 at 02:39 PM

    Yes, select only this option and environmentshell as environment.

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 31, 2016 at 02:36 PM

    Hi Vadim,

    Thanks for your suggestion. This is production system. Is it safe to do it?

    Thanks

    Jingjing

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 31, 2016 at 02:54 PM

    Hi Vadim,

    Running into issue with it :(.

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 31, 2016 at 04:07 PM

    Sorry, I told you to select ONLY one option!

    Why do you:

    Add comment
    10|10000 characters needed characters exceeded