MIGO Unable to store information without posting items.

MIGO The delivery note cannot be added and saved in the MIGO transaction without posting one of the items. I just want to store te delivery note and someone else is responsible for posting the items. How can I solve this problem?

Regards, Jochen

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

5 Answers

  • Best Answer
    Sep 02, 2008 at 01:58 AM

    Hi,

    Tell someone to post the GR document and then you can take that material document number and later you can go into MB02 and key in the document number and then enter the delivery note number and save.

    But if you would like to enter the delivery number and then the other person to enter the GR it is not possible as the system prompts to save the document. or you can hold the GR document and then later it can be processed and saved.

    Or make this delivery number mandatory in the GR document and make any one person to enter both the information and save the GR document.

    Thanks & Regards,

    Kiran

    Add comment
    10|10000 characters needed characters exceeded

    • Hi,

      It is a functionality of Gate Entry functionality.

      Near the gate they post GR to 103 Mvt type which is Qty valuated but not value valuated

      and then actual GR is done at 105 Mvt Type. by doing 105 it is valuted both Qty and value

      You can make the Field mandatory in SPRO.

      For Tocde wise go to field selection and make the field as required not optional.

      Thanks & Regards,

      Kiran

  • Sep 02, 2008 at 01:58 AM

    Hi,

    If any other person is responsible for posting it..then either keep on hod or on park....so that later on it'll get posted....

    Pls see the differences b/w hold and park...

    This may help you...

    Regards

    Priyanka.P

    AWARD IF HELPFULL

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 02, 2008 at 06:58 AM

    Why can't the receiver itself enter the delivery note number? The delivery note is usually the paper that accompanies the goods and that is used as a basis when posting the receipt.

    It is not possible to maintain this number at a later time using change material document transaction.

    If you want post it as information earlier, why dont you maintain it as ASN (advanced shipping notification) in the confirmation tab of the purchase order?

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 03, 2008 at 04:56 AM

    i believ you should devlope a z report for the gate entry as it was done by one of the client

    they have created a z report for the gate entry and the selection screen was having fields vendor material qty etc. and once the gate entry was done then were going for the migo

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 03, 2008 at 05:27 AM

    Hello

    Adopt delivery to PGI process,

    One can make a delivery thru VL10D agt PO and another person can post that delivery with additional delivery note, anything. May be you need some configuration setting for this

    Regards