Hi,

While creating maintenance order I am able to enter estimated cost in header tab but I couldn't above to see the same amount in cost tab. What could be the reason for the above.

I am trying to enter the costs in estimated values like labour chanrges, misllenious cost etc in estimated cost before order release. But i couldn't able to enter any type of cost there.

Is there any config setting requires for the above?

Could any body help me out on this please?

Regards

Srinivas

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks for all

Regards

Srinivas

Former Member
0 Kudos

Hi srinivas,

Whats the error system is showing?

Just take the costs tab and and inside that take the costs tab just beside overview tab.U can enter the estimated costs there.

regards

ebin

Former Member
0 Kudos

Hi Ebin,

In cost tab beside of overview It is displaying but not allowing to enter any cost. it is in grey ...

Regards

Srinvas

Former Member
0 Kudos

Nothing is there in Value Cat Description..

Regards

Srinvas

peter_atkin
Active Contributor
0 Kudos

Have you configured the value categories in the IMG?

PeteA

Former Member
0 Kudos

Hi Pete,

Thanks for your ans. I got the solution. I have to configure the same(Valution Cat).

If you have any standard step for this sent me the link.

or else I can do.

Thanks Pete,

Regards

Srinivas

peter_atkin
Active Contributor
0 Kudos

Srinivas,

As standard, the estimated costs can only be entered during CRTD status.

You can either enter the costs at header level or via the cost tab (value category level), but not both...

Try removing the estimated costs in the header, then enter then via the cost tab.

If you've released your order - then its too late and there's nothing (standard) you can do..

PeteA

Former Member
0 Kudos

Even though I couldn't able to enter any type of costs in cost tab, Order was in CRTD status only. I haven't given any cost in header datta.

Regards

Srinivas