Transfer control Strategy

Hello all,

What is relevenece of using transfer control in costing variant

why we use it.

suggest

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Sep 01, 2008 at 12:34 PM

    Hi prem

    It is for partial costing. The purpose of partial costing is to prevent the system from creating a new cost estimate for a material when costing data already exists. Instead, the existing costing data is simply transferred into the new cost estimate. This improves performance.

    You can create at TCode OKKM

    Cheers

    Srinivas