schduling problem

former_member214153
Active Participant
0 Kudos

sap guru.

when we make a planned order convert into production order

than it show scheduling date in next month .but it show in another planned is show it current month date.

Pls suggest me what is the reason for this problem.

thanks and Regards,

Anurudh Singh

Edited by: anurudh singh on Sep 1, 2008 1:57 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please check ur operations activity time in routing.

which u have maintained.

also check ur inhouse production time in MM02 for both the products.

Thanx & regards,

Nilesh Ithape

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

see the planned order dates and capacity overloading.