Skip to Content

schduling problem

sap guru.

when we make a planned order convert into production order

than it show scheduling date in next month .but it show in another planned is show it current month date.

Pls suggest me what is the reason for this problem.

thanks and Regards,

Anurudh Singh

Edited by: anurudh singh on Sep 1, 2008 1:57 PM

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 01, 2008 at 12:03 PM

    Hi,

    Please check ur operations activity time in routing.

    which u have maintained.

    also check ur inhouse production time in MM02 for both the products.

    Thanx & regards,

    Nilesh Ithape

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 01, 2008 at 12:03 PM

    Hello,

    see the planned order dates and capacity overloading.

    AM

    Add comment
    10|10000 characters needed characters exceeded