on 09-01-2008 12:10 PM
Hi,
Purchase Requisition is not generating against the sales order type--ZOD1.But purchase requisition another 4 sales document type.
Please give me the solution which field I have to check & how to solve this PR issues.
Thanks,
Rash.
Hi Rashm
Check the assignment of the item category to the document type in t code VOV6
Also have a look if the schedule line is the same as it is present in the other sales document types where the PR is getting generated
Hope this helps
Thanks
Akasha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check Points for Purchase Requisition.
1.Check in material master- Item Category Group. For Eg-BANS (If Std is maintained)
2. Check Item Category- TAS(if Std) is appearing in Sales Order.
3. Check Schedule Line type CS (if std) in v0v6 that order type should be NB & item category-5.
Revert if not resolved
Regards
Amit Gupta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rash
ZOD1 is not a standard one. Anyway, please check in VOV7, select your item category and see whether you have checked the box for the field [Create PO Automatic]
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I hope you are triggering CS as your schedule line category. Even if another schedule line category is triggered ensure that:
1) Order type is NB in schedule line category
2) Item category is 5 in schedule line category.
Regards,
GSL.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.