Purchase Requisition is not generating against the sales order type--ZOD1.But purchase requisition another 4 sales document type.

Please give me the solution which field I have to check & how to solve this PR issues.

Thanks,

Rash.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Rashm

Check the assignment of the item category to the document type in t code VOV6

Also have a look if the schedule line is the same as it is present in the other sales document types where the PR is getting generated

Hope this helps

Thanks

Akasha

Former Member
0 Kudos

Hi,

But I have already checked with other document with ZOD1.But i couldnot found any difference for generatin PR.

please give me the solution which perticular field or assignment I have to check.

Thanks,

Rash.

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Check Points for Purchase Requisition.

1.Check in material master- Item Category Group. For Eg-BANS (If Std is maintained)

2. Check Item Category- TAS(if Std) is appearing in Sales Order.

3. Check Schedule Line type CS (if std) in v0v6 that order type should be NB & item category-5.

Revert if not resolved

Regards

Amit Gupta

Lakshmipathi
Active Contributor
0 Kudos

Dear Rash

ZOD1 is not a standard one. Anyway, please check in VOV7, select your item category and see whether you have checked the box for the field [Create PO Automatic]

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi,

In VOV7 which item category I have to check for create automaic PR.

Please give me the solution for this.

Thanks,

Rash.

Edited by: rashm gupta on Sep 1, 2008 1:30 PM

Former Member
0 Kudos

I hope you are triggering CS as your schedule line category. Even if another schedule line category is triggered ensure that:

1) Order type is NB in schedule line category

2) Item category is 5 in schedule line category.

Regards,

GSL.