Skip to Content
avatar image
Former Member

How to move configuration from production order to batch

Hello,

when I post production order confirmation using co15, some materials movements are generated (movement type 101) and because material has activated batch management, system creates new batch number and insert this batch number to material movements. I need to copy information about configuration (CUOBJ) from production order to batch (CUOBJ_BM).

Is there some standart solution or do I need to edit some user-exit or BADi?

Thanks&regards,

Jirka

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Sep 01, 2008 at 02:47 PM

    Dear,

    What do you mean by configuration?

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 01, 2008 at 02:47 PM

    Hi,

    Create a class via CL02 and give it a characteristic.

    For the characteristic you'll need to say where it comes from in CT04 additional data tab, table is probably AFKO, the field is up to you. Also set is as not ready for input and 'no cahracteristic values allowed'

    Basically i think you're looking at the table and fields available within batch characteristics.

    Regards,

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear,

      Use one of these user exits

      MBCFC003 Maintaining batch master data upon goods movements

      MBCFC004 Maintaining batch specifications upon goods movements

  • Sep 01, 2008 at 04:04 PM

    Hi,

    Have a look at tranasaction OMCV in addition to batch classification and characteristic documentation. OMCV offers extended classification option against movement types which may offer you a solution.

    Regards,

    Add comment
    10|10000 characters needed characters exceeded