Electricity Power - in BOM

Hi Experts

My client wants to put the Electricity power as a component in the BOM since power is one of the major consumption material.

I suggested them to add the power cost in the Activity price, but they want to see the variance of power consumption (Plan Vs Actual).

Please suggest me what material type should i select?

Or anyother way to solve this issue?

Thanks & Regards

Bala

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • Best Answer
    Sep 01, 2008 at 11:07 AM

    Dear Balamurugan,

    I'm not sure but try out this,

    Generally Electricity falls under Pipeline material with material type PIPE.

    check the following link for further understanding,

    [Pipeline material|http://help.sap.com/erp2005_ehp_03/helpdata/EN/4d/2b926443ad11d189410000e829fbbd/frameset.htm]

    on The other hand ,

    You can create an activity type say Elec and assign formula through formula parameters.

    You can maintain an unit of measure and a value in the routing for each operation for which ever is required.

    (provided if you know a rough/exact value of power consumption).

    I dont know how far the second answer will be helpful to you.

    Regards

    Mangalraj.S

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 01, 2008 at 11:23 AM

    Hi,

    If they producing the power from their own plant using DGenerators and then using the same for plant usage you can make it as a stock item (l) . You can add it as a component in the BOM and the UOM as KWH.

    Earlier i had worked with one cement industry client and we maintained the power as a stock material.

    Regards

    Pragash

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 01, 2008 at 10:46 AM

    Hello

    if it is necessary then make it as pipeline material

    Regards

    AM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 01, 2008 at 11:20 AM

    Hi Bala Murugan,

    In one of my project, ELECTRICTY is defined as material.

    It is added to the BOM.

    You have to define it as PIPELINE material.(Material type PIPE).

    It can be captured as an activity in std value key or as a parameter in BOM, where u enter this value at the time of confimation.

    Srini

    Add comment