Dear Expert

We issue RM through MB1A against production Order.But By Mistake Production Order entered in the second screen of MB1A which update co data but not withdrawn Qty in production order component.Is there any way to update withdrawn Qty where RM is issued as Unplanned Issue? RESB-ENMNG is not updated

Accepted Solutions (0)

Answers (2)

Answers (2)

JL23
Active Contributor
0 Kudos

if MSEG-RSNUM field has a reservation number then you can correct the planned consumption with a report from OSS note 656469 - Correction report f. incorr. withdrawal quantities in order

Otherwise live with it as is and do it better in future.

read also 1899046 - Withdraw Quantity (RESB-ENMNG) Zero for Reservation

JL23
Active Contributor
0 Kudos

Why not just cancel it and doing it right then

former_member541431
Participant
0 Kudos

Dear Sir

Number of Documents are 2K / Month and I want to update data of Last one year.