Hi All,

Is there any report to show which material that i already input in CJr2 (detail planning)

Step 1. CjR2

2. choose layout 1-701 CE planning

3. Input WBS and CE

4. Go to edit and detail planning

5. Input material no dan plant , quantity, when it save it goes to the total value. But i could not find report to show material that was assigned.

Plz advice.

Cheers,

Nies

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

No answer

Former Member
0 Kudos

Your thread is not quite clear. Please elaborate.

Regards

Sreenivas

Former Member
0 Kudos

Hi Sreenivas,

I go to CJR2

Then I put WBS element : let say ABCD

Cost element : 630600

Then I select august and go to Edit - detail planning

I choose item category M and put material number and qty

then save it and post

After that i try to use standard report S_ALR_87013532 ..its only show the plan cost.

I wish there is standard report to check which material has been assigned in the WBS and CE.

Cheers,