Report to Check material attach in CJR2 (detail planning)

Hi All,

Is there any report to show which material that i already input in CJr2 (detail planning)

Step 1. CjR2

2. choose layout 1-701 CE planning

3. Input WBS and CE

4. Go to edit and detail planning

5. Input material no dan plant , quantity, when it save it goes to the total value. But i could not find report to show material that was assigned.

Plz advice.

Cheers,

Nies

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 04, 2008 at 12:34 PM

    No answer

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Sreenivas,

      I go to CJR2

      Then I put WBS element : let say ABCD

      Cost element : 630600

      Then I select august and go to Edit - detail planning

      I choose item category M and put material number and qty

      then save it and post

      After that i try to use standard report S_ALR_87013532 ..its only show the plan cost.

      I wish there is standard report to check which material has been assigned in the WBS and CE.