I had small query in planning board in maintenance order. I have created a maint order and when i was trying to use functionality of planning board, after giving proj profile its not going to next screen and giving the following screen and message number, can any one help me in this regard.

This is the following error i was getting,

Order XXXXXXXX has no requirements in the eval. period, so there is no display

Message no. CY139

Diagnosis

Orders were selected that have no requirements in the evaluation period or they have requirements at other work centers from those that were selected (for example, by the overall load of a person).

Procedure

Adjust the evaluation period in the time profile.

Munny.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Sep 01, 2008 at 09:07 AM

    hi

    check whether you have entered the work hours required in the operation tab and also check CR12 for your workcenter whether factory calendar and version has selected

    regards