Serial number entry after posting delivery doc......

hi experts....

we have a requirement in which in the standard sales cycle of Sales order->delivery document posting ( PGI)-> invoice billing the client wants that serial number entry (which is done at the time of PGI) should be done after invoicing(at the end of the day) because as per the business practice of the client, its not practically feasible for the client to enter serial numbers at the time of selling the finished material. The client manually records the serial numbers on the invoice copy and enters the serial numbers for the respective invoices at the end of the day.

Now while testing the client scenario we found that once PGI & invoicing has been done without entering the serial number for the material, the system does not accept any serial number assignment for that material after the completion of sales cycle.

So is there any solution in which serial number can be entered for a material whose PGI and invoicing has been completed?

Thanks & Regards

Vikas Hali

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 01, 2008 at 11:13 AM

    Hello,

    As you know the system may not allow to enter the serial number details in the delivery --> Extras --> Serial numbers field, once the delivery is completely PGI'ed and invoiced.

    But you may change the same in the table by debug mode. You need to update serial number in the material document in the table level also. Contact your ABAP expert, he may be able to guide you properly.

    Prase