estimated costs in PM order

hellow friends,

After the order is released, i would like to maintain the

estimated costs in the costs tab but it is inactive.

Does anybody know if it posible to active this option

or it available when the order status is "created" only?

regards,

avi

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • Best Answer
    Aug 31, 2008 at 07:35 PM

    Hi,

    The estimated cost field on order header and fields on cost tab are closed for input once the order is released. It is not possible to change this via customizing or other settings.

    -Paul

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 01, 2008 at 03:35 AM

    hi

    You can only specify the estimated cost before the order is released.once the order is released you cannot specify the estimated amount.

    regards

    thyagarajan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 01, 2008 at 03:56 AM

    Dear Avi,

    As posted by thiyagrajan, estimated cost can't be added once the order is released. Reason behind it is this that the person who is creating order can fill this cost upon his technical experience. So accordingly higher authority will come to know the approx. cost of the job planned in the order. After that if management feels that they can go ahead with cost, they they release the order for durther processing.

    I hope this will clear your concept for estimated cost entry.

    Regards,

    Kaushal Rai

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 01, 2008 at 07:52 AM

    Estimation of Costs in Maintenance Orders

    Estimated costs can be entered in the following ways:

    1) As an overall total on the header data screen

    2) Divided into value categories in the cost overview

    The cost elements 692000 and 693000 are grouped under value category "Internal activities".

    To enter the estimated costs broken down into the individual value categories, you must have grouped the cost elements for these value categories in the Customizing for the Project System.

    Features

    You can only specify estimated costs for the order until the order is released.

    In contrast to planned and actual costs, estimated costs are not updated in the Plant Maintenance Information System (PM-IS).

    Activities

    After the estimated costs have been entered, the system sets the the status Costs estimated for the order.

    It may help you

    Srinvas