Former Member

Marking and releasing for PREM profile in CK40N

Hi Gurus,

We are using Repetative mfd process for which we have config to the Product cost collector (PCC)and we sucessfully executed KKF6N.

But when we are trying to run CK40N,we are not able to get the marking and release(fields)in the cost estimate tab.The system is displaying only SELECTION,Struc EXP,Costing,Analysis.

Whether i have missed any config setting for PCC.if not what i have missed out.

Revert

Regards

Pran

Edited by: Praveen Singh on Aug 31, 2008 2:10 PM

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 01, 2008 at 09:14 AM

    Dear,

    Define standard costing variant PPC1.

    Run std cost estimate CK11N for material.

    Release STD cost estimate either by CK40N or by CK24.

    Hope above will helpful to you.

    GOPAN.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 31, 2008 at 01:16 PM

    Hi Praveen, You need to use CK24 to mark and release the standard cost estimate since CK40N can only create cost estimates in a mass scale. Hope it helps much! Cheers!

    Add comment
    10|10000 characters needed characters exceeded