how to activate available control without budget distribution?

in OPS9 in spro, the budget profile, Overall budget and annual budget indicator are both not set, which means Avail. control is against annual budget. But if i don't distribute the annual budget (the annual budger is zero),the available control doesn't work.

Does that mean you have to distribute the budget before you can active the available control ?

thanks guys.

regards,

tiger wu

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Sep 02, 2008 at 06:59 AM

    Run the Tcode CJBV - Activate Availability Control, this will activate availability contron for your project.

    pradeep

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 02, 2008 at 07:25 AM

    Please see message below in the next post.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 02, 2008 at 07:28 AM

    This message was moderated.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 02, 2008 at 07:58 AM

    Even you if you dont distribute the budget, the availability control should work.

    Did you maintain the tolerence limits for the transactions which you need to have the availability control??

    Run CJBV to activate the Availability control..

    I think your availability control is not working because you have zero budget..

    KAP

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      You are correct in the context of this posted topic, the budget should be distributed so that it is greater than zero, in case of annual budget control.

      In general, when we are doing an overall budget control, there is no need to distribute the budget unless that is the requirement.

      KAP