Dear All,
I have a six level Bill of Material ( BOM ) .I am using planning strategy 20 make-to-order producton.
There is no stock for any of these materials.
Now when i try to run mrp on sales order basis it is not planning for all the levels of the BOM.The MRP Stops planning at 3 or 4th level.The MRP Run does not give any error.
Is there any setting to carry out MRP out MRP for all level of BOM?
I checked the setting in 0001 plant and compared them with my plant they are same.THE SYSTEM IS DOING MRP IN 0001 PLANT FOR ALL LEVELS
so pleses help me on these issue.
Regards
Prashant
Hi Prasant ,
If you have already checked all customization setting , check some easy access setting .
For the levels for which BOM is not exploding ( Multilevel) is active or not .
Material below 4 levels having MRP type PD and not ND . Even if its reorder point and plant stock is above reorder pt it will not generate order proposal .
MRP views are properly maintained for materials .
Neal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Check in CS02, is is there any material in a level which is having MRP Type ND.
if it is there this may be the problem.
AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I Hope you have done the all the settings , but check othe OMDY -planning run Error handling ,
Select the Planning run
Increse the Propsals.
Maximum proposal should be incresed from 50 to 999
Then check the MRP RUN
Hope you will get the solution
Thanks and regards
E.Rambabu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hy Prashant,
If you want to carry out MRP with MD50 for all levels of BOM then check this things,
For all the BOM components (up to last level) check in MRP 4 view of Material master
- Individual / Collective - It should be Individual or Individual/Collective.
If is maintain as Collective then you will not get planing Proposals though MD50.
- For all BOM headers Materials (Fert , Halb ) check in MRP 4 view for MRP for Dependent requirement should be maintain as Dependent requirement are Planned
Check the above things and if not maintain then maintain it and then run MRP with MD50.You will get the Planing proposals for all levels of BOM.
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use MD50 to run MRP against sales order. In this system only plan upto FERT level.
Again do MRP run for FERT material by MD02 tcode. Now system will plan upto ROH level.
If it is not solved revert back.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.