cancel
Showing results for 
Search instead for 
Did you mean: 

unable to carry out MRP for make-to-order

Former Member
0 Kudos

Dear All,

I have a six level Bill of Material ( BOM ) .I am using planning strategy 20 make-to-order producton.

There is no stock for any of these materials.

Now when i try to run mrp on sales order basis it is not planning for all the levels of the BOM.The MRP Stops planning at 3 or 4th level.The MRP Run does not give any error.

Is there any setting to carry out MRP out MRP for all level of BOM?

I checked the setting in 0001 plant and compared them with my plant they are same.THE SYSTEM IS DOING MRP IN 0001 PLANT FOR ALL LEVELS

so pleses help me on these issue.

Regards

Prashant

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi Prasant ,

If you have already checked all customization setting , check some easy access setting .

For the levels for which BOM is not exploding ( Multilevel) is active or not .

Material below 4 levels having MRP type PD and not ND . Even if its reorder point and plant stock is above reorder pt it will not generate order proposal .

MRP views are properly maintained for materials .

Neal

Former Member
0 Kudos

Hello,

Check in CS02, is is there any material in a level which is having MRP Type ND.

if it is there this may be the problem.

AM

Former Member
0 Kudos

Hi,

I Hope you have done the all the settings , but check othe OMDY -planning run Error handling ,

Select the Planning run

Increse the Propsals.

Maximum proposal should be incresed from 50 to 999

Then check the MRP RUN

Hope you will get the solution

Thanks and regards

E.Rambabu

dhaval_choksi3
Active Contributor
0 Kudos

Hy Prashant,

If you want to carry out MRP with MD50 for all levels of BOM then check this things,

For all the BOM components (up to last level) check in MRP 4 view of Material master

- Individual / Collective - It should be Individual or Individual/Collective.

If is maintain as Collective then you will not get planing Proposals though MD50.

- For all BOM headers Materials (Fert , Halb ) check in MRP 4 view for MRP for Dependent requirement should be maintain as Dependent requirement are Planned

Check the above things and if not maintain then maintain it and then run MRP with MD50.You will get the Planing proposals for all levels of BOM.

Regards,

Dhaval

Former Member
0 Kudos

Hi,

Use MD50 to run MRP against sales order. In this system only plan upto FERT level.

Again do MRP run for FERT material by MD02 tcode. Now system will plan upto ROH level.

If it is not solved revert back.

Regards,

Dharma

Former Member
0 Kudos

Hi

Even u can use MD02 transaction directly for MRP run. It will plan till the last level for the materials in the same plant.

No need ro run MD50 and then MD02.

Thanks & regds