How to copy a task in CPI-DS

Mar 27 at 07:08 AM

16

avatar image

HI Team,

I have to simulate a task In CPI-DS hence looking to copy the task but I dont see any option in Actions... Can anyone help me here

Regards,

Satya

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Ashish Goel Mar 30 at 09:52 AM
0

Hi Satya,

To copy a task : Select the task -> Goto More Action -> Replicate -> Select the project where you want to copy it.

Hope it helps.

Thanks,

Ashish