Dear SAP Experts,
During the Creation of process order creation there is a major problem regarding the Basic start date and end,because as we are using Scheduling type as Forward scheduling and the input is as start date the system should calculate the finish date automatically according to the Master recipe standard value.
But it takes the value Four months from the date of Start date
As attached screen shot the start date is 10.01.2018 and the finished date is automatically calculated as 14.04.2018 and this is happening particularly only for this specific material .
For all other materials thee dates are calculated correctly.
Please give solutions asap as i checked all the configurations and material master but could not come with a solution.
i have checked OPUZ in which the date is opuz.png
Please give your valuable inputs it woild be appreciated.