I have the limited messages,How to all configure the below?

The following working replies are needed:

  • Abort chain and set chain status to "Error".
  • Abort chain and set chain status to "Completed".
  • Restart this step.
  • Restart and Hold this step.
  • Restart chain from the beginning.
  • Rerun chain status handlers as if the step completed with status "Completed".
  • Rerun chain status handlers as if the step completed with status "Error"
untitled.png (10.2 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

G.M. Blom Nov 14, 2016 at 01:12 PM
0

Hello,

For BW process chains not all actions are available that you have on CPS regular JobChains. This is due to the differences between how BW process chains work and how CPS job chains work.

Regards Gerben

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Nov 14, 2016 at 02:28 PM
0

Hi Gerben,

Thanks for your reply but this is something that is needed for CPS regular chain(SAP CRM) only for adding more functionality so that we don't have to resubmit the entire chain instead replying through operator message would trigger the chain at any desired step.

Regards,

Hitanshu.