I have created Production order & GI & GR done for complete Qty, then added additional QTY through CO02 to PRD order then output activity pricess increased, but WIP is not getting calculated(REL), the process which i followed has anything wrong for not getting WIP calculation?

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi,

If actual GR quantity in your order is greater than or equal to your planned quantity, order status turns to Delivered (DLV) and in this case WIP isn't calculated.

It might be that even though you've changed the quantity via CO02, planned quantity is still smaller than or equal to the actual quantity - so status is still DLV.