Some production which have been created and in previous year come into cost settlements through co88 in July 2008. the client does't have WIP process and they have to create and settle the production orders for SFG/FG in the same month. Ex: One production order (SFG) was created on 11.01.2008 and completed on 13.01.2008. As the system picks the PO's collectively at the time of settlement how some production orders are missed out from cost settment at that time??

Please clarify

thanks in advance

mammu.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks Shiva.

former_member335796
Active Contributor
0 Kudos

Hi,

Check the Production Order statuses for the SFG production Order.

The Rule:

If the Order Status is DLV or TECO, then only the Order will be part of Settlement process.

If the Order Status is REL, then only the Order will participate in WIP Process.

But, you do not have the WIP Process in Place..

So, the Order must have put to DLV or TECO recently..

Check this and revert for further discussion..