Skip to Content
0
Former Member
Aug 26, 2008 at 01:24 PM

Production Order for SFG

52 Views

Hi Experts,

Some production which have been created and in previous year come into cost settlements through co88 in July 2008. the client does't have WIP process and they have to create and settle the production orders for SFG/FG in the same month. Ex: One production order (SFG) was created on 11.01.2008 and completed on 13.01.2008. As the system picks the PO's collectively at the time of settlement how some production orders are missed out from cost settment at that time??

Please clarify

thanks in advance

mammu.