Standard Cost in Production Order

512 Views

Dear Sir,

We have a scenario that initial Std Cost was Rs 10000 for a specific HALB Material as per the released cost run . Subsequently a Production Order was released for this Material . After release of Production Order , we have modified the Std Cost for the Material to Rs 12000 .

Now we want that Production Order should refer the Std Cost as 12000 not the earlier one of 10000 .

In report S_ALR_87013127 against this Production Order Std Cost is still appaering as Rs 10000 only .

Pl guide us as how can the Production Order read the Std Cost as 12000 not the 10000 .

Pl help us .

Rgds