Hey Experts,

I am creating new work schedules in our system where off days will fall in between the weeks e.g Sunday and Monday, Tuesday and Wednesday...Friday and Saturday instead of Saturday and Sunday. I created this in the PWS

99 Z7SM UNION 001 ZOFF Z1SU Z1SU Z1SU Z1SU Z1SU ZOFF

99 Z7SM UNION 002 ZOFF Z3SF Z3SF Z3SF Z3SF Z3SF ZOFF

99 Z7SM UNION 003 ZOFF Z2SU Z2SU Z2SU Z2SU Z2SU ZOFF

then i set work schedule rules and generated but its not picking the Sunday and Monday as the off days

Accepted Solutions (0)

Answers (1)

Answers (1)

ImranSajid
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

In the Set Work Schedules Rules and Work Schedules IMG activity where you configure your WSR pay special attention to the "Ref. date for PWS" and "Start point in PWS". These will control the rotation of your schedule. Try changing the value in the Start point in PWS and then regenerate the work schedule and see the behavior to understand it.

Regards,

Imran

former_member193210
Active Contributor
0 Kudos

We've always used Monday January 1st as the Reference Date for PWS.