Dear experts,

We would like to implement few additional checks and validations when a financial plan version status is changed. Are there some user exits that are available? or if you could guide us to code fragment that could be enhanced?

Viele Grüße, Gudrun

Accepted Solutions (1)

Accepted Solutions (1)

raymond_amalraj
Explorer
0 Kudos

Hi Gudrun,

status-management.png

You may want to check if you can leverage the user exit class in the above screenshot for this purpose. This is accessible via SPRO node "Make Settings for Status management" under Project Cost and Revenue Planning

Regards,

Raymond.

Former Member
0 Kudos

Thank you! Raymond.