on 08-23-2008 11:41 AM
Dears ,
Can I Create PIR with Production Version Specific
Best Regards
Rami
Hy Rami,
Yes you can select required Prod. Version With PIR itself.
To do the same follow below Path,
MD61/MD62 --- > Go to Schd. Line Tab ---> Go to Settings Menu --->
Production version.
After pressing that Tab for Prd. Version you will find Column for Prod. version gets Activated and there you can select your required Prd. Version.
System will explod the BOM and Recipe as per that Selected Prod. Version during MRP run.
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes.
in MD61,inside screen click on schedule line and foloow the menu path
setting -->production version.
Production version column appears.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.