Create PIR with Production Version

former_member182449
Participant
0 Kudos

Dears ,

Can I Create PIR with Production Version Specific

Best Regards

Rami

Accepted Solutions (0)

Answers (2)

Answers (2)

dhaval_choksi3
Active Contributor

Hy Rami,

Yes you can select required Prod. Version With PIR itself.

To do the same follow below Path,

MD61/MD62 --- > Go to Schd. Line Tab ---> Go to Settings Menu --->

Production version.

After pressing that Tab for Prd. Version you will find Column for Prod. version gets Activated and there you can select your required Prd. Version.

System will explod the BOM and Recipe as per that Selected Prod. Version during MRP run.

Regards,

Dhaval

Former Member
0 Kudos

Yes.

in MD61,inside screen click on schedule line and foloow the menu path

setting -->production version.

Production version column appears.

former_member182449
Participant
0 Kudos

Dears,

i create two requirement for the same material with different production version

I need during the MRP Run Create two planned order for each requirement

Regards

Rami

Former Member
0 Kudos

is it not creating 2 line items?

did you make the lot size in matrial master as EX?

dhaval_choksi3
Active Contributor
0 Kudos

Hy,

It depends on your Lot size procedure.

Try with changing value in MRP data 4.

- only with Production version

- Individual Requirement.

Regards,

Dhaval