BADI to set task and checklist status based on phase status

Hi,

We have a requirement to set the system status and user status of all the task and checklist to complete when the phase that they belong to is set to status complete.

I have implemented the badi DPR_EVENTS which gets triggered when Phase is completed.

My issue is this badi does not work when the phase is completed as system does not allows the change any data of tasks or checklist items since the phase is complete. I get a message stating "you cannot change the status of this task".

I tried reseting the complete status of teh phase and setting the tasks status and then setting the phase status back to complete. But this does not seem to be working.

Is there any way to achieve this requirement?

Thanks,

Simmi

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Aug 22, 2008 at 09:09 PM

    Since we could not do it on Phase complete event we did it for some other event