cancel
Showing results for 
Search instead for 
Did you mean: 

Labor efficiency calculation

former_member254501
Active Participant
0 Kudos

Hi I need to develop report for labour efficiency...the doubt i have is do we need to include labour setup time also in calculation...for ex... std labour time =no of product× (labour time + labour setup time)

Accepted Solutions (1)

Accepted Solutions (1)

BijayKumarBarik
Active Contributor
0 Kudos

You have your won logic on process calculation and you can go for development!

In general efficiency=(output/input)x100 but in your case- consider maximum production quantity /ideal expected production quantity

Answers (0)