Interesting twist. I need to take a material and bundle into a BOM. I want the material when entered to be replaced by the BOM, which includes the same material and others. The normal replacement rule is creating a never ending loop of adding the bom over and over which I can see the logic but how do I make the case I need to work.
Material A replaced by Material B (plus material A)
Kerry,
I would suggest that you maintain such replacement in a custom table and adjust the BOM during explosion in your orders - planned order or production order using BAdI's/enhancements.
Rajen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kerry,
Please correct if I am wrong, you want to create a BOM for a material which has that material also?
Like BOM for material A having components as A,B etc...
Can this be achieved by making BOM for A and then adding that as "recursion allowed".
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.