Hi

How can we send the Asset for Subcontracting, M/C for repair to vendor

Without retiring the same.

With Regards

Niti Narayan

Accepted Solutions (0)

Answers (3)

Answers (3)

deiva
Active Contributor
0 Kudos

Hi,

1. Material type u201CUNBW u2013 Non Valuatedu201D to be configured with only quantity updation.

2. Stock for materials received from any of the work centres for replacement / repairs to be taken into stock using MB1C 501 movement for the MMR created under UNBW material type.

3. A sub-contract Purchase Order is to be created specifying the GL account / Cost Centre to which the servicing charges are to be debited and the same material attached as component which is to be provided to the Sub-Contractor.

4. Issue of material to the Sub-contractor referring to the PO using MB1B movement type 541.

5. Create the out put for referring the Gate Pass Print out to the above mentioned document (MB1B, movement type 541)

6. The Material leaves the Plant premises with the above mentioned Gate Pass and stock of the material moves out from u201CUnrestricted useu201D to u201CProvided to Vendor Stocku201D.

7. Receipt of goods after repairs - MIGO

8. Invoice verification for the Servicing charges u2013 MIRO (FINANCE)

9. Issue of material to the respective cost center using MB1A , movement type u201C201u201D, there wonu2019t be any Accounting entry passed for this issue as the material involved is of Material type u201CUNBW u2013 Non Valuatedu201D

only.

kunal_ingale
Active Contributor
0 Kudos

hi

yes u can do it

create a po for subcontracting in which ur finished and raw material will be the same

also u can try for service po but in this case u cant take ur material out of company

regards

kunal

Former Member
0 Kudos

Hi,

Create a service PO for repair. Send the material out through 541 movement type.receive material back with 542 movement type.