Hi all,
We need to change quantity of PR that's generated by PS module, I know there is no standard solution but could the Abaper interacts for that ?
You must change the purchase requisition from the module where it was created, how else shall the triggering processes know that they don't get the quantity that is needed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is not the right way of a business process, the inventory controller has to speak with PS person and it needs to be adjusted there.