Cost (Rate) and Revenue (Rate) Values are not appearing correctly

0 Kudos

Hi Fellows

While doing valuation in Monthly Planning, /CPD/FTRATE (Cost Rate) and /CPD/FTSRRTE are showing strange numbers in Infor Provide /CPD/PFP_R01 or Queries. However Cost Plan, Revenu Plan, Transaction Cost etc. are showing correct results. If I debug MM valuation or SD Valuation both are showing correct results.

Any clue. What should be checked?

Regards

Hafiz

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi Raymond

Please see the screen shot

In this example Cost Rate is 190 and Cost Plan is 190*100. Rev Rate is 250 Rev Plan is 250000. Can you please give any idea where could this problem come from.

raymond_amalraj
Explorer
0 Kudos

Hi Hafiz,

Can you post a screenshot or sample plan line item details which you find it strange for cost rates.