Set-Up Material in Production Planning

Mar 20 at 12:52 PM

28

avatar image

Dear PP Gurus

I Need your help to map the business requirement in SAP.

When ever they setup a machine, they will test with some raw materials whether the setup is maintained properly or not. Because of this activity the Quantity is reduced but its not scrap.

Now they are mentioning it as scrap and it is creating a huge confusion in scraps

Example: I am creating 10 mts tube first i'll make 1mt tube if all goes ok then ill proceed

So the user wants an alternative to post the consumed material.

How can we map this requirement in production planning module

Thanks in Advance

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

K V Kumar Mar 22 at 09:24 AM
0

Hi,

for the initial setup produced qty, ask them do the partial confirmation of the production order with that qty and during this confirmation ask them to consume the input materials stocks. After that once they complete the production ask them to do final confirmation with the remaining qty.

Hope this helps.

Thanks

Kumar