is it possible to roll back a copied tenant to its original state after doing developement in it?

Mar 20 at 10:23 AM

52

avatar image

Hi All,

I am exploring the possibility of a possible scenario:

if a refresh request of a tenant(QA/Prod) was made with full copy(including PDI solution & config) and post getting a copy, development was done on it including new PDI solutions patch moving and overwriting existing PDI solutions. so at any point of time if decided to roll back to its original state as per the development. is it possible? is there a provision for that?

Best Regards,

Suman Pattnaik

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Anant Acharya
Mar 20 at 12:49 PM
0

Dear Suman,

I guess if you have any active restore point then you can achieve this if not NO.

Hope this helps.

Regards
Anant

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Anant,

Thanks on this. SAP confirmed on this as well, but immediate question to it is that will this restore point consist of all the master data, configuration settings, PDI solutions already existed when restore point was created and roll back is 100%? since, changes will happen post restore point w.r.t to above parameters and as I understood, PDI restoration would not be possible during restore. Also exploring all master data/Transnational data(If deleted/changed) would be a challenge too?

Best Regards,

Suman Pattnaik