Skip to Content
0

Process order - Capacity check not proposed any new dates

Mar 16 at 10:21 AM

47

avatar image

Hi Friends,

During Process order creation/release , we check the capacity check button but system couldn't have proposed any new dates where capacities are available during finite scheduling. Overall profile SAPSFCG013 assigned in OPJK, OPU5 and OPUZ

please find the snapshots.

thanks,

sankarancor1-capactiy-check-issue.jpg

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

sankaran muthusamy Mar 19 at 10:15 AM
0

Hi Caetano,sapsfcg013.jpgsapsfcl010.jpg

thanks for your comments.

I'm testing manual creation of process order but still same (nothing proposed new dates)

in CORY I'm using SAPSFCG013, confirm capacity and finite scheduling are checked

in OPU3 detailed scheduling checked too.

in OPJK using SAPSFCG013 too.

How to setup correct capacity scheduling correctly?

Thanks in advance,


sapsfcg013.jpg (61.5 kB)
sapsfcl010.jpg (87.8 kB)
Show 2 Share
10 |10000 characters needed characters left characters exceeded

Hello Sankaran

The time horizon defined in the standard profile SAPSFCG013 may be to narrow and you may not find available capacity, therefore, system will not propose any dates. You should try to create a new profile (as a copy of the standard profile SAPSFCG013) and extend the planning horizon.

Regards,
Caetano

0

Hi Caetano,

Thanks again. I tried to change the time period and assigned to profile which we are using, then i create new process order but still same issue. its not propose any new date ?

please find the attached snapshot for time period details

time-profile.jpg

cor1-capactiy-check-issue-same.jpg

0
Caetano Almeida
Mar 18 at 10:16 PM
0

Hello

Make sure your time horizon defined in the profile is includes dates with free available capacity.

Regards,

Caetano

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Caetano,sapsfcg013.jpgsapsfcl010.jpg

thanks for your comments.

I'm testing manual creation of process order but still same (nothing proposed new dates)

in CORY I'm using SAPSFCG013, confirm capacity and finite scheduling are checked

in OPU3 detailed scheduling checked too.

in OPJK using SAPSFCG013 too.

How to setup correct capacity scheduling correctly?

Thanks in advance,

0
sankaran muthusamy Apr 09 at 02:03 PM
0

Hi Caetano,sapsfcg013.jpgsapsfcl010.jpg

thanks for your comments.

I'm testing manual creation of process order but still same (nothing proposed new dates)

in CORY I'm using SAPSFCG013, confirm capacity and finite scheduling are checked

in OPU3 detailed scheduling checked too.

in OPJK using SAPSFCG013 too.

How to setup correct capacity scheduling correctly?

Thanks in advance,

Share