on 03-16-2018 8:03 AM
Hi All,
I am facing issue for a BOM ,in which for many materials dependant rquirment getting generated till 2019 based on planned order but for 2 components its not getting generated after april 2018...when I check MD04 of those material I can see dependent requiremnt are till 2019 but from another header component...Not sure whats happening with this specific bom and those specific material only...checked BOM and Material no new revision level or changes...kindly suggest what to check if anybody faced this kind of issue
Hi,
Check the affected components validity in the BOM. Maybe these components only valid to April 2018.
Best Regards,
Krisztina