on 03-15-2018 9:34 PM
Hi - I have Planned Independent requirements created for a project (WBS Element). I want these PIRs consumed when Goods Received on Work Order. I used planning strategy 11, but in MD04 the the PIRs are not showing under the project section, rather plant section. My requirement is that the PIRs should show under the project section in MD04 and that they should be consumed when GR on order. Can you suggest how I achieve this.