on 08-13-2008 11:29 AM
Hi Experts,
I am working on a make to order scenario.
PROBLEM
After running MRP the scheduling dates appearing does not consider the data in the routing. ie the standard parameter value entered in routing is not consider for scheduling.
WHAT I HAVE DONE
1. I have entered standard scheduling formula in the workcenter
2. created the sceduling profile, production scheduler in IMG and assigned it to material
3. created scheduling parameter for planned order with order type KD in IMG
4. I have ticked on the sales order/ WBS in explosion control
5. i have enterde MRP type PD and Planning stratergy as 20 in MM01
6. Scheduling type is backward scheduling
7. While running MRP Planning mode in "2" and scheduling is "2"
Where am i going wrong.
Regards
Samarth
Hi,
In OMIW un-check the SO/WBS BOM. Entry in this field is not required if you plan with Planning Strategy 20 and if there is no WBS involed.
Whether the routing data maintained is appropritate?
Plan for more quantity you may get the diffrenece after planning..
Regards,
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Brahmankar,
In production order also it is not taking routing data for scheduling. in actual calculation as entered in routing it req 5 days for operation to finish. But here it is taking just 1 day. and in operation overview for each standard parameter it is showing the same start and fifish day.
Regards
Samarth
hi Brahmankar,
I have activated the scheduling indicator in op00. I have created this control key in OP00, when i use this control key scheduling does not take place. but when i use the standard control key PP01 scheduling occurs. What might be reson since i have created the key by copying it from PP01
Regards
Samarth
Hi,
I think your peroblem has been solved.
Control key is nothing but a key that specifies how an operation or a sub-operation is processed in functions such as orders, costing or capacity planning.
The following are examples of processing types managed by a control key for operations and sub-operations:
External processing
Completion confirmation
Printing
Scheduling
Costing.
To check for which control key like PP01,PP03 what indicators has been included goto to T Code OPJ8,Just double click on each control key and you can find for that control key what indicators has been choosen.
If useful rewards suitable points
Redards,
R.Brahmankar
Hi Brahmankar,
I have got one more enquiry. all the indicators active in control key PP01 (in house prod) is active in the control key that i have created. then what might be the reson that when i put my control key schedulin does not take place where as scheduling occurs when i put PP01.
Regards
Samarth
Hi Samarth,
Please check
Order types define the routing selection OPL8 that selected routing must having your control key with scheduling active.
OPU3- Define Scheduling parameters for Production order?
In material master have u assigned a production scheduling profile for the corresponding order type?
Regards,
R.Brahmankar
Hi,
Check the scheduling dates by increasing your requirement or routing time.
For MTO scenario, create demand by sales order, not by MD61.
Do the following settings in OPU5, select your plant & scheduler (*).
In this select Adjust scheduling - Adjust basic dates dependent req to Opn dates.
Now rerun MRP by Delete & recreate mode with Lead time scheduling. Check the result.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.