on 08-13-2008 6:12 AM
We want to apply a planning calendar to a sub-contract vendor so that Chinese New year is bloked out for them and our system doesn't plan deliveries from them that cannot happen. Does anyone know how to do this?
Hi,
You can try following steps.
Create one Planning calendar in MD25 specifying each period as yearly periods.
Maintain Lot size as PK(MRP 1 view) and Planning calendar(MRP 2 view) in material master for the components subcontracing.
After MRP system will group all the requirements in each period and creates PR according to the planning calender.
Regards,
R.Brahmankar.