Hi All,
I would like to create coding mask therefore, the user must follow the coding mask when create PRoject/wbs
My project code is : XXXXDVPLHYYNN
XXXX = plant
DV = division
PLH = prject type
YY = year
NN = number of project.
What the best coding mask should i use and how to create it?
2nd. What the function of graphics profile for WBS date planning.
Project System - Dates - Date Planning in WBS -Specify Graphics Profile for WBS Date Planning
Appreciate for your advice.
Nies
Nies,
For Coding Mask I would suggest you to use an alphabet in the begining for ex- N-XXXX-DV-PLH-YY-NN. And you create it in Tcode OPSJ and also see OPSK.
Following points might help you more on this:
-Coding Masks are important if you need to have some intelligence in the way your Project Definition and WBS Elements appear to the user.
-They can reflect the structure of a project
-They can control project Identification
-They only relate to Project Definitions and WBS Elements
-They determine what special characters are permitted to separate the structure view
-They are not connected to Profiles u2013 the u2018Project IDu2019 used in Operative or Template projects determines the mask
-Different Masks can be used with one or many Project Profiles
Not sure about the other part of your problem. Hope it helps.
Thanks.
BS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
really appreciate for your advice. Project definition : PHRE01PLH01 ; My wbs code shown below : This code is only for one project profile, for other project using another format : Should i use coding mask ?
Level WBS
1 PHRE01PLH0801
2 PHRE01PLH0801-TP
3 PHRE01PLH0801-TP-SB
3 PHRE01PLH0801-TP-IM
3 PHRE01PLH0801-TP-TB
3 PHRE01PLH0801-TP-PJ
3 PHRE01PLH0801-TP-PS
3 PHRE01PLH0801-TP-PL
3 PHRE01PLH0801-TP-PG
3 PHRE01PLH0801-TP-JT
3 PHRE01PLH0801-TP-PT
2 PHRE01PLH0801-PP
3 PHRE01PLH0801-PP-PJ
4 PHRE01PLH0801-PP-PJ-UD
4 PHRE01PLH0801-PP-PJ-UR
Please advice.
Cheers,
Nies
Honestly, your mask is tooooo..big. How you can expect anyone to remember or punch in such lenghty code while posting anything onto level 4 WBS element (whose lenght is 22 Char).
Ask business if they really need such project codes, why is it required to capture plant,project type in project code when you have specific master fields for them? It's you call, try to keep it simple.
Regards
Sreenivas
HI Sreenivas,
appreciate for your input. Actually, it has some meaning for it.
PHRE: Plant
01 : Division
PLH : Project Type
08 : Year
01 : Project number
TP : 1 level activity in plantation (land clearing for example)
SB : 2nd level of activity.
1 PHRE01PLH0801
2 PHRE01PLH0801-TP
3 PHRE01PLH0801-TP-SB
3 PHRE01PLH0801-TP-IM
3 PHRE01PLH0801-TP-TB
3 PHRE01PLH0801-TP-PJ
3 PHRE01PLH0801-TP-PS
May i have your suggestion ? what the impact if i use TP and SB using network activity rather than WBS? the business process using Activity based costing.
Cheers,
NIes