Hi,

I got one task from my company,I need to change some abap code.

what i need to do .I need to create one change request for that or i need to change directly.

If i need to create change request,Please tell me how to do that.

please give me the solution.

regards

chinna

8 REPLIES 8

Former Member
0 Kudos

HI ,

When u change an existing code , it will automatically ask for Transport Request Number. So , change ur code as per requirement , create a new Tr no .

0 Kudos

hi kumar,

If the same user changing the code two times(two different times) ,

on that case no need to create the transport request or create one more.

0 Kudos

Hi ,

If the existing Tr no is not transported then no need of creating a tr no.

0 Kudos

Hi Chinna,

Unless the current transport request is not transported, there is no need to create a new one and you can make any changes. But once you have transported, any changes made, should be assigned to new request. In fact, the previous request will not be available once you have transported it.

Regards,

Chandra Sekhar

0 Kudos

hi chandra,

My object was not transported,previously different user was changed,now i need to change that code,

again i need to create the new transport.

Former Member
0 Kudos

Former Member
0 Kudos

Hi,

Check the below steps.

1. In SE38 or SE80, You have to change your code first.

2. Click 'Save' [CTRL+S] Button in Toolbar.

3. if the program doesn't have any TR, it will show one dialog screen and ask the TR. Here you have to click 'Create' Button.

4. You have to give the TR Description. and click 'OK'.

5. Again Click 'OK'. and then your program assigned to New TR.

Regards,

Boobalan S

Former Member
0 Kudos

Hi,

U can do changes for that object what ever changes u want if it is not realeased (se09) then no issues .....

if it got realeased then also you can do changes for that object but , when ever ur saving that object it will ask for new request no. then u have to create a request ... if already created a request for that task assing it ...

hope helpful

Raghunath.S