Skip to Content
0

Activity Confirmation Control in CJ20n

Mar 16 at 11:46 AM

78

avatar image

Hi All,

Please help me to solve this issue "

We restrict the activity to confirm priority wise means while going to confirm 2nd activity Ist activity should be confirmed. , but my problem is that system not allowing to confirm next activity unless and untill we save the project after confirmation.

But my client requirement is that without saving the project they want at a time confirm many activities with restriction rule means Ist activity must be confirmed before going to confirm the 2nd activity priorities wise. They want to save the project at last after confirmation of all the completed activities.

Please provide solution for that.

Thanks ,

Sanjita

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Maria Terence Mar 18 at 04:42 AM
0

Hi Sanjita,

There is no standard options available, you need to have some logic in place during the confirmation to mark the activities which are confirmed by user action and on save it can update all.

Contact your abaper, should be able to solve it.

Regards

Terence

Show 4 Share
10 |10000 characters needed characters left characters exceeded

Hi,

Thanks to answered.

Please provide me some logic points , so i can explain to my ABAPer.

Thanks ,

Sanjita

0

Hi Sanjita,

I am not sure how this technically works, but check with the Abaper.

Internal table to check whether the Operation is Checked with Final Confirmation, yes or no. Based on that, when the user confirms the next operation, it has to check the Internal Table whether it is confirmed.

This should allow them to save. You need to check with Abaper.

Regards

Terence

0

Hi Sir,

Our ABAPer were working on that but they didn't get option without saving of ist activity move for Next , So They Define one Intermediate Save Button . It is working good in DEV Client while saving through intermediate Button project is not going to close , so user can at time confirm more activities.

But problem arised when TR transfered to QAS many errors are coming , pls find below error, ABAPer not able to solve this now.

Any body have an suggestion please provide me .

int-med-button.jpg (90.6 kB)
0

Hi,

You need to check why it is working fine in DEV and not in QA. Is both DEV and QA are in same version ?

Refer this thread.

https://archive.sap.com/discussions/thread/3606824

Regards

Terence

1