Hi Friends,

please give me the required configuration settings for capacity planning in work centre in detail. my requirement is to view the load in each work centre. should i give finite scheduling or not. i am getting an error while creating production orders "No reqmts/caps exists or not relevant to finite scheduling"

please give solution

regards

Arun Kumar R V

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Arun

Hi,

The following configuration steps involved in the capacity planning:

SPRO --> IMG --> PRODUCTION --> CAPACITY REQUIREMENT PLANNING

Capacity Requirements Planning:

1) Define time units

2) Define Capacity Category

3) Set up Capacity Planner.

4) Define parameters

5) Define Standard value key.

6) Define Move time matrix.

7) Define Setup matrix.

😎 Define Control Key.

9) Define Shift Sequence.

10) Define Key for performance efficiency rate.

11) Define Formula parameters.

12) Specify Scheduling type.

13) Set up Production scheduler group

14) Select Automatically.

15) Define Scheduling parameters for Production orders

16) Define Scheduling parameters for networks.

17) Define Reduction Strategies planned/ production orders.

18) Define Reduction Strategies for network/process orders.

19) Define Control Profile.

20) Define Selection profile.

21) Define time profile.

22) Define Evaluation profile.

23) Define Strategy Profile.

You can follow these above configuration steps in capacity planning

Yes you need to active your all work center for the finite scheduling at the bottom of capacity view.

Hope clear to you.

Regards,

R.Brahmankar

Former Member
0 Kudos

This message was moderated.

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Use all standard SAP configuration,Capacity Leveling Profile.

Define time profile in OPD2.

Define the strategy profile in OPDB

Define the Overall profiles in OPD0.

Then only you need to to active your all work center for the finite scheduling at the bottom of capacity view in work center.(CR02)

Then run MRP with scheduling- 2 Lead time scheduling and capacity planning.(MD02)

You will get your capacity requirement in CM01, or CM25/CM21.

In rem you can use MF50.

Please try and revert back if you have any query on the same

[Capacity Planning|http://help.sap.com/saphelp_46c/helpdata/en/8a/a5a3154adc11d189740000e8322d00/frameset.htm]

Regards,

R.Brahmankar

Rewards if useful

Answers (2)

Answers (2)

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Rakesh,

There is quite a bit of useful config in the Best Practices Production Planning doc, including a section on cap planning.

http://help.sap.com/saap/sap_bp/BBLibrary/Documentation/142_BB_ConfigGuide_EN_IN.doc

Best Regards,

DB49