MRP Data in Material Master

Dear all,

In material master we have maintain the

MRP Type : ZB, Rorder point as 100

Lot size : FX

Fixed Lot Size : 500

Now with these setting is possible that system creates the PR for individual material say for quantity say 2.

If the required quantity is 100 how PR will generated?

I want the system to give the Gross level PR only not individual PR.

How can achieve this?

Regards,

SP

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2008 at 08:31 AM

    Hi,

    If your stock level falls below 100 as you have mentioned Reorder point, the system will create the PR for 500 qty as Fixed lot size is 500.

    Regards,

    Raviraj

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 11, 2008 at 08:36 AM

    hi,

    We maintain the our Reorder point as well lot size so as to provide the system some details to hit the procurement to generate the PR's....

    Also we donot use MRP if the req. to generate PR's for very small qty (yes can be done, but not recommended)...

    Now,

    As per your provided details,

    the PRs will be always generated for 500 qty only...as given in the lot size..

    Hope it helps...

    Regards

    Priyanka.P

    AWARD IF HELPFULL

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2008 at 08:38 AM

    Hi,

    Reorder Point is 100

    You have Lot size as FX (Fixed) --> 500

    However your stock level is below reorder point (100) PR will generate for 500qty...then your stock will update with stock qty (Earlier)+500.

    If you want to generate 100 PR's only... you have to change the Fixed Lot Size as 100 from 500 then you can acheive your target

    Thanks & Regards

    Anilkumar Dalai

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 11, 2008 at 10:08 AM

    Hi,

    MRP is mainly configured for a material so that tere would not be any need for manual checking of the stock so as to create a PR.

    The parameters which you have specified for a particular material like reorder point and lot size will help in planning for a particular material.

    If you need only Qty of two (Less) then there s no need of configuring a MRP for that material

    And lot size is also decided basing on certain other factors like

    1) Lead time

    2) Transportation costs involved in procuring the material etc

    So ifyou want to generate PR for a qty of 100 then you need ot change the lot size

    I hope this gives you clarity

    Thanks & Regards

    Pavan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.