Hi.
I am trying to set up Plan Driven procurement on SRM 5.0 and ECC6.00.
I used MRP to create purchase requisition. After the exection of MRP,
I found no entry created in the ERPTRANS table for the PR documents
generated by MRP.
However, after changing the MRP origin PR document with ME52N,
a entry for that PR document was inserted in the ERPTRANS table.
Also, I manually created a purchase requisition using ME51N,
an entry was inserted in ERPTRANS table too.
Are there any special settings necessary for MRP?
Thanks in advance for any advice.
HN