Hi

I would like to know the Process of Stock Transfer Order of movement type 641.I would like to know the Tcodes along with the process.

Points will be awarded

Thanks in advance

Subhash

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2008 at 04:26 AM

    Hi

    you follow follwing steps in STO

    1. make STo - me21n

    2 delivery by supplying plant - vl10b

    3 PGI by supplying plant - vl02n

    4. proforma invoice VF01

    5. Goods receipt by receiving plant MIGO

    6.invoice of freight - MIRO

    Regards,

    Vijay

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 11, 2008 at 04:25 AM

    hi,

    Has no pc right now...but will update reg. mvt type...

    STO

    Following are the steps:

    1.Create a vendor for the company code of receiving plant, using account group :0007 using T-Code XK01.

    2 Assign this vendor to Delivering plant

    Go to XK02 >Purchasing view>Extras>Add. Purchasing data>Plant

    3. Create internal customer with the sales area of the vendor. Go To XD01

    4.In Pricing procedure determination relevant to STO, assign document Pricing Procedure and customer pricing procedure appropriate for STO to get the pricing in the invoice.

    5.Maintain condition records for the relevant pricing condition.

    6. Some more setting for STO: Go to MM> Purchasing > Purchase Order > Set up STO> define shipping data for plants > Go to Receiving plant >assign customer here & Supplying SA (for billing) to Receiving plant here

    7. Go to MM> Purchasing > Purchase Order > Set up STO> define shipping data for plants > Go to Supplying plant and assign the sales area of receiving plant.

    8. Go to MM> Purchasing > Purchase Order > Set up STO> assign delivery Type & Checking rule

    Assign the delivery type to document type. In this case, Delivery type NLCC is assigned to Document type NB

    9. Go to MM> Purchasing > Purchase Order > Set up STO>Assign document Type, One step Procedure, Under delivery tolerance

    Assign the document type NB to supplying plant and receiving plant

    10. After all settings , Create the STO using T-Code:ME21n and Save.

    11. Create Delivery :VL10G

    Click on the Background Button after selecting line item

    A message is flashed : See log for information> next Click on Log for delivery creation Button >click on line item>click on document button to get Delivery document No

    12. Picking, PGI:[VL02n

    13. Billing:VF01n

    Save the document and its done

    Hi

    Follow the below steps to to make STO between two plants ( different company codes).It is also called as Inter Company STO.....

    1)Create one Customer Master in XD01 with respect to Supplying Plant Sales Area and assign this Customer no with Receiving Plant in OLME ->PO -> set up STO->Define shipping data for plant and for the supplying Plant assign the above sales area.( Make sure,In Customer Master,sales Area Tab: you are maintaining shipping condition)

    2) For Receiving Plant Pur. Org and Co.Code Combination create Vendor master in XK01 and in this vendor master assign the Supplying plant in Pur.Org.Data screen ->Extras --> Add.Pur.data

    3) OLME ->PO -> Set up STO------>For your supplying plant assign document type NB, Delivery type NLCC and Checking Rule RP

    4)then For your supplying Plant and receiving Plant assign Document type NB

    5)Make sure you are maintaining Sales View for the material at supplying Plant and in Sales /Gen plant Data view maintain Availability check, Loading group and Transportation group.

    6) In SPRo-- >Logistics execution > Shipping ->Basic shipping functions ->Shipping point Determination >assign shipping points -> For your Loading group,Shipping Condition and Supplying plant combination,Assign shipping point

    these are the configuration settings you have to do in background.

    Then Create STO from Receing Plant in ME21N with document type NB.

    Based on that STO, Create Delivery in VL10B from supplying Plant

    Do PGI in VL02N from Supplying plant

    Do GR in MIGO at Receiving Plant keeping Outbound delivery as a ref. document.

    Now your STO bet. two plants belongs to diff. Co.Codes will be completed.

    2)Follow the below steps to to make STO between two plants belongs to same company codes).It is also called as Intera- Company STO.....**

    1)Create one Customer for Supplying Plant Sales area and assign this Customer no with Receiving Plant in OLME---> PO -


    > Set up STO -


    > define Shipping Data for plants. and maintain the same sales area in your Supplying plant.

    2) In OLME---> PO -


    > Set up STO.....for your Document Type: UB and Suppying plant Combination assign Del. Type NL and Checking rule RP

    3) In OLME---> PO -


    > Set up STO...for your Supplying Plant and Receiving Plant combination Maintain Doc. Type : UB

    Make sure you are maintaining Sales View for your Material at Supplying Plant.

    4) Maintain Shipping point at, SPRO----> Logistics Execution -


    > Shipping -


    > Basic Shipping Functions -


    > Shipping Point Determination for Plants.....there for your Loading group,Shipping Condition, Shipping Plant combination maintain Shipping plant..

    Now Create STO in ME21N with Doc.type: UB at Receiving Plant.

    Then Create Delivery in VL10B from Supplying Plant...

    Then Do PGI in VL02N from supplying Plant.

    Then do GR at Receiving Plant based on Outbound Delivery at Receiving Plant...

    Regards

    Priyanka.P

    AWARD IF HELPFULL

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 11, 2008 at 04:31 AM

    STO CONFIG:

    The following steps have to be followed in order to configure stock transport order between two plants.

    1. Create a vendor for the Company code of the receiving plant using account group 0007 via T-Code XK01.

    2. In the purchasing data view assign the supplying plant and the schema group

    3. Create customer with the sales area of the vendor.

    4. The shipping conditions, the delivering plant and the transportation zone determine the route in the STO.

    5. In the pricing procedure determination relevant to the STO assign document pricing procedure and customer pricing procedure to get the pricing in the invoice.

    6. Maintain condition records for pricing condition.

    7. Maintain carrier as a partner in the customer master.

    8. In OMGN select the supplying plant and assign the company code and sales area. Similarly select the receiving plant and assign the company code and sales area (The company code to which the plant is assigned to).

    9. Assign the delivery type and checking rule to the document type.

    10. And finally, assign the purchasing document type to the supplying plant and the receiving plant.

    11. Create the STO using T-Code ME 21N and save.

    12. Check for release strategy if any and release using T-Code ME 28.

    13. Create delivery in background using VL10G.

    14. If delivery is created, it is an indication of correct configuration and master data creation.

    Stock transfer between two plants in different company codes is known as inter company stock transfer.

    Material should be maintained in both supplying and receiving plant MM01

    Stock should maintain only in supplying plant MB1C

    Create receiving plant as a customer in supplying plants company code and sales area XD01

    Assign this customer number in receiving plant details OMGN

    Assign supplying sales area in supplying plant details OMGN

    Assign delivery type NB for in combination of supplying/ receiving plants.

    Create STO ME21N

    As it is normal there in the item details we should get shipping date i.e. customer number

    Go for Delivery VL10B

    Shipping point *****

    Select PO go for execute

    then select the delivery then go for delvy ............create delvy,,,, delvy number generated.

    Goods Issue VL02

    Delvy doc **********

    Click on picking

    enter the picking qty

    Click on PGI

    in the mean time check in the PO history you will get the details

    Goods receipt MIGO

    Stock overview the stock will be updated....

    Check the below link

    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2ba31643ad11d189410000e829fbbd/frameset.htm

    Stock transfers that include deliveries and billing documents/invoices are only possible between plants belonging to different company codes.

    If you want to carry out a cross-company-code stock transport order with delivery but without a billing document, you must set the Relevant for Billing (data element FKREL) indicator in Customizing of the item type to "blank" (Not relevant for billing).

    The following applications are involved in this type of stock transfer:

    • Purchasing (MM-PUR) in entering the order

    • Shipping (LE-SHP) in making the delivery from the issuing plant

    • Billing (SD-BIL) in creating the billing document for the delivery

    • Inventory Management (MM-IM) at goods receipt in the receiving plant

    Invoice Verification (MM-IV) at invoice receipt in the receiving

    Transfer of goods from one location to another location, it may be between plants within the same company code or in different company code's plants.

    within the company code, but plants,

    receiving plant will raise the STO in Supplying/issuing plant-ME21n,

    Supplying plant will deliver the goods to receiving plants ,

    then we need to pick n post the Goods Issue-VL02n,

    now when we can observe that the STO qty will be added into receiving plant and reduced in Delivering plant,

    To do this, we need do prior customization in SPRO-IMG,-

    material should be created in both plants( receiving & Supplying)

    -maintain the stock only in supplying plant

    -create a dummy customer in supplying plant's sales area(if u have one sales area, create in tat comp code n sales area)

    -assign this customer number to receiving plant's details along with the sales area,

    -Assign the STO doc type(UB) to Supplying plant, along with checking rule

    -Assign the Del type (NL/NLCC) to Supplying n receiving plant.

    Stock Transport Order:

    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b911d43ad11d189410000e829fbbd/content.htm

    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b917843ad11d189410000e829fbbd/content.htm

    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b918543ad11d189410000e829fbbd/content.htm

    u can also use the SAP building block

    with delivery

    http://help.sap.com/bestpractices/BBLibrary/html/P36_IntStockTransDel_EN_IN.htm

    without delivery

    http://help.sap.com/bestpractices/BBLibrary/html/P38_IntStockTransWithoutDel_EN_IN.htm

    regards

    kunal

    award if helpful

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2008 at 09:13 AM

    Hi

    I did the configurations for STO document type UB, inter company code with movement type 641. I created the STO and it got saved. But when I use Tcode vl10b and give the PO number and execute it, nothing is displayed. Can u tel me why that is and what i should do to rectify it.

    Thanks and Regards.

    Subhash

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2008 at 09:34 AM

    hi

    please check the delivery date you are entering. it should be of the range what you mentioned in STO.

    Regards,

    vijay

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2008 at 09:50 AM

    Hi

    you just enter the shipping point and date range and execute .

    no need to enter STO no.

    you will get.

    Regards,

    Vijay

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.