Project Structuring in Assembly processing

Former Member
0 Kudos

Hi ,

The created standrad project is with the coding as shown below

X-00000000 WBS Level 1

X-00000000.01 WBS Level 2

X-00000000.01.01 WBS Level 3

X-00000000.02 WBS Level 2

X-00000000.02.01 WBS Level 3

But when the project is triggerred from sales order in assembly processing system takes coding as

X-00000000.10 WBS Level 1

X-00000000.10 WBS Level 2

X-00000000.10.10 WBS Level 3

X-00000000.10 WBS Level 2

X-00000000.10.10 WBS Level 3

why the system is not taking the same code as there in std template.

Pl suggest

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Check SD/PS assignmnt indicator on the Control tab page of the standard project definition in CJ92. Remove the tick and try again.

Regards

Answers (1)

Answers (1)

Former Member
0 Kudos

check the following link which provides the details about the project numbering in case of assembly processing

http://help.sap.com/saphelp_erp60_sp/helpdata/en/4c/225eed46e611d189470000e829fbbd/frameset.htm

regards

Murali